Exemption from approval - building notification
Beim Genehmigungsfreistellungsverfahren wird der unteren Bauaufsichtsbehörde ein Bauvorhaben unter Vorlage der Bauunterlagen zur Kenntnis gegeben.
Details
Certain building projects within the scope of a qualified development plan must be notified in the approval exemption procedure in accordance with Section 61 of the Thuringian Building Code (ThürBO), provided that there are no exemptions and exceptions from the provisions of the development plan.
In contrast to the building permit procedure, there is no obligation for the building supervisory authority or the municipality to check the planning and construction in the case of an exemption from approval. The building supervisory authority only intervenes at its own discretion during construction and subsequent use if there is a suspicion of conduct in breach of building regulations. It is obligatory to inspect building documents in the interest of the building owner and, if necessary, to request additions and corrections as a basis for proper construction.
The municipality can demand that a simplified building permit procedure be carried out in accordance with § 62 ThürBO instead of the permit exemption procedure.
Documents
Required documents | Further information |
---|---|
Thuringian application form |
The building application form is used for the notification, to be found under -> Forms the correct type of procedure, in this case exemption from approval, must be selected (tick) |
Statistical survey form | Survey forms of the official statistics in Thuringia(link is external) |
Authorisation to submit building documents and specialist planner's certificate | as a rule by seal or certificate |
Building description |
|
Current excerpt from the real estate map (cadastral plan) | Geoinformation - excerpts from the real estate map |
Site plan (scale not smaller than 1:500; usually 1:250) |
if applicable, partial plans with:
|
Floor plan drawings, views, sections, possibly photos of the existing building (§ 8 ThürBauVorlVO) | usually scale 1:100 |
Fire protection certificate (for building class 4 and 5, as well as special buildings) | You will find the corresponding form under Forms |
Neighbour participation / statement of the adjoining neighbours (§ 69 ThürBO) | prescribed in case of deviations from neighbour-protecting regulations (§ 66 ThürBO) => signature on site plan, section and views with reference to the deviation (preferably all neighbours on the same copy) |
Consent of responsible district chimney sweep master | applies as recommendation, as far as not legally prescribed |
Expert opinion and other proofs |
|
Declaration on structural engineering evidence in accordance with § 65 ThürBO |
|
Structural engineering verification: in accordance with § 65 ThürBO, only in the case of compulsory testing (usually 2-fold) |
|
In contrast to the building permit procedure, only 1 copy of the documents must be submitted. These remain with the building regulations department.
The building documents listed depend on the project applied for, only those required in each case are to be submitted. As a rule, not all of them will be required, in individual cases others may be added.
Opening hours
Tag | Zeiten |
---|---|
Montag | 08:00 – 12:00 und 13:00 – 16:00 Uhr |
Dienstag | 08:00 – 12:00 und 13:00 – 16:00 Uhr |
Mittwoch | keine Sprechzeiten |
Donnerstag | 08:00 – 12:00 und 13:00 – 18:00 Uhr |
Freitag | 08:00 – 12:00 Uhr |
Hinweise
Um vorherige Terminvereinbarung wird gebeten.
Fees
Services | Fee |
---|---|
Implementation of the approval exemption procedure | free of charge |
Legal basis
- Thuringian Ordinance on Building Documents and Notifications by Building Authorities (Thüringer Bauordnung (ThürBO))
- Thuringian Ordinance on Building Documents (ThürBauVorlVO)
- Notice of enforcement of the Thuringian Building Code (VollzBekThürBO)