Set up construction site

Setting up a roadworks site with a traffic order

A traffic order for setting up a construction site is a special permit. It is required for the use of public paths, roads or squares if the ground is to be dug up for a construction site, something is to be stored/set up there or a pipeline is to be laid in the airspace. Traffic regulation measures are necessary.

You also need a special use permit(link is external) in accordance with Section 18 of the Thuringian Road Act.

Your application should be submitted 14 days before the start of use to allow sufficient processing time. Please note that it can take up to a week to send your application by post.

You also need a special use permit in accordance with Section 18 of the Thuringian Road Act.

A completed application form is all that isrequiredto give advance notice of the establishment of a construction site.You will find the document under Downloads.

Please make sure that you complete the form clearly and precisely in all points. The more precise the information you provide, the easier it will be for the person responsible to issue the permit.

Tag Zeiten
Montag 08:00 – 16:00 Uhr
Dienstag 08:00 – 16:00 Uhr
Mittwoch geschlossen
Donnerstag 08:00 – 18:00 Uhr
Freitag 08:00 – 12:00 Uhr

Außerhalb der Öffnungszeiten erreichen Sie uns nach telefonischer Absprache.

An administrative fee is charged for the permit, which depends on the importance of the road, the area occupied and the duration of the special use. In addition, a fee is payable for the work site of the traffic area, which is also calculated according to the above criteria.